INVITATION TO BID

Sealed bids for the construction of the City of La Pine, Finley Butte Road Pedestrian
Improvements Project, addressed to Public Works and Planning Admin, Kelly Notary,
City of La Pine, Oregon will be received until 2:00 PM local time at City Hall, 16345 Sixth
St, P.O. Box 2460, La Pine, Oregon, on May 19, 2020 and then publicly opened and read
at 2:00 PM at City Hall, in La Pine, Oregon. Bids shall be clearly labeled: Finley Butte
Road Pedestrian Improvements Project.

Scope of Work:
Improvements generally include the construction of concrete sidewalk, electrical utility
trench, electrical conduit installation and associated incidental improvements. Project is
funded through the State of Oregon Small City Allotment Grant Program.
The City estimates the cost of improvements at $100,000.

Construction plans titled, Finley Butte Road Pedestrian Improvements Project dated
April 2020, consisting of 6 sheets and project specifications are herein incorporated into
the Request for Bid for detail of the overall scope of the project including the scope of
services for this portion of the project. All workmanship, materials, and conditions
shall conform to the 2018 Oregon Standard Specifications for Construction and the
City of La Pine, Oregon 2016 Standards and Specifications.

This is a Public Works Contract and subject to Oregon Bureau of Labor and
Industries (BOLI) Prevailing Wage Rates (only if project costs exceed $50,000)
Effective January 1, 2020 for Region 10.

Completion:
It is the intent of the City of La Pine to achieve substantial completion by August 31, 2020.

Project Timeline:
Advertisement April 28, 2020
Bid Closing May 19, 2020
Bid Review May 20, 2020
Intent to Award May 20, 2020
Council Contract Award May 27, 2020
Anticipated Work Period June 1 to August 31, 2020
Substantial Completion by August 31, 2020